AL Alaya 'a Residential Cluster A
Building Plot (N34-128 ) & ( N34-129)
FINSHES WORKS
عقد التشطيبات
PROGRESS REPORT
UP TO 1-9-2026

P2 CONTRACT BASIC INFORMATION

The Construction Of MEP, Finishes, And Landscape Work For Al Aliya'a Residential Buildings - Cluster (A), Plot (N34-128) & Plot (N34-129)
P2 / 128-129

CONTRACT DATA

Project Name
The Construction Of MEP, Finishes, And Landscape Work For Al Aliya'a Residential Buildings - Cluster (A), Plot (N34-128) & Plot (N34-129) Project
Total Value Original
S.R. 171,126,263
Project Start Date
23/06/2024 G
Project Finish Date
23/02/2026 G
Finish Date Revised
31/10/2026 G
Duration Original
20 Months
Duration Revised
28 Months

PERFORMANCE SNAPSHOT

Elapsed Duration
92.33%
Remaining Duration
7.67%
Planned Progress
98.92%
Actual Progress
98.90%
Variance
-0.02%
Planned
98.92%
Actual
98.90%
Elapsed
92.33%
Remaining
7.67%
Sources: 128-129.docx and PROGRESS.xlsx. This page is linked to P2 project information and summarizes the contract baseline, revised timeline, and current progress position.

128-129 S-CURVE

Dynamic curve generated from 128-129 S CURVE.xlsx
Source: S CURVE sheet
0 46.2M 92.4M 138.6M 184.8M 643K 449K 1.1M 2.4M 7.1M 7.2M 7.8M 7.6M 12.5M 12.0M 10.1M 7.9M 9.0M 8.4M 9.8M 9.2M 8.9M 11.8M 8.7M 5.6M 3.5M 7.5M 5.9M 1.3M 1.3M 1.3M 1.3M 1.2M 5.3M 7.4M 3.4M 8.8M 9.5M 13.0M 10.4M 6.0M 13.0M 10.0M 8.8M 10.4M 7.7M 6.1M 2.7M 11.0M 6.1M 4.6M 5.4M 3.4M 3.6M 3.2M 643K 1.1M 2.1M 4.5M 11.6M 18.8M 26.5M 34.1M 46.6M 58.6M 68.7M 76.6M 85.6M 94.0M 103.7M 112.9M 121.8M 133.7M 142.3M 147.9M 151.4M 158.9M 164.8M 166.1M 167.4M 168.7M 169.9M 171.1M 0 0 0 5.3M 5.3M 12.7M 16.1M 24.8M 34.4M 47.4M 57.8M 63.8M 76.8M 86.8M 95.6M 106.0M 113.8M 119.8M 122.5M 133.5M 139.6M 144.2M 149.5M 152.9M 156.5M 159.8M Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 Dec-25 Mar-26 Jun-26 Sep-26 Cum Planned RevisedCum Actual ProgressMonthly Planned RevisedMonthly Actual
Finishes 128-129 project image
FINISHES 128-129

P2 PROJECT DETAILS

AL ALAYA 'A RESIDENTIAL - FINISHES 128-129
128-129 interior - bathroom
ON TRACK
CONTRACT VALUE
171,126,263 SAR
PLANNED PROGRESS
98.61%
ACTUAL PROGRESS
98.52%
SPI
1.00

Progress Performance

Planned
98.61%
Actual
98.52%
Variance
-0.09%

Schedule Status

89.08%ELAPSED
Elapsed89.08%
Remaining10.92%
Actual Value168,593,594
Remaining Value2,532,669
AL Alaya 'a Residential Cluster A
Building Plot (N34-142 )
FINSHES WORKS
عقد الخرسانات والتشطيبات
PROGRESS REPORT
UP TO 1-9-2026

P3 PROJECT DETAILS

AL ALAYA 'A RESIDENTIAL - CLUSTER A STR & FINISHES 142
AL ALAYA 142 project photo
ON TRACK
CONTRACT VALUE
117,477,457 SAR
PLANNED PROGRESS
98.00%
ACTUAL PROGRESS
97.73%
SPI
1.00

Progress Performance

Planned
98.00%
Actual
97.73%
Variance
-0.27%

Schedule Status

89.92%ELAPSED
Elapsed89.92%
Remaining10.08%
Actual Value114,810,719
Remaining Value2,666,738

142 S-CURVE

Dynamic curve generated from 142 S CURVE.xlsx
Source: S CURVE sheet
0 31.7M 63.4M 95.2M 126.9M 226K 1.8M 3.7M 4.3M 2.7M 4.0M 4.5M 3.4M 4.0M 4.3M 4.7M 5.2M 6.2M 6.5M 8.1M 9.8M 9.2M 8.2M 5.5M 4.4M 3.5M 3.7M 4.0M 4.7M 1.0M 7.2M 5.9M 4.4M 4.8M 2.3M 8.6M 4.9M 3.6M 2.3M 5.1M 6.6M 4.7M 6.4M 5.1M 4.9M 5.5M 2.5M 5.3M 5.8M 2.6M 3.8M 2.1M 2.2M 2.3M 226K 2.0M 5.7M 10.0M 12.6M 16.7M 21.1M 24.6M 28.5M 32.9M 37.6M 42.8M 48.9M 55.5M 63.6M 73.4M 82.5M 90.7M 96.2M 100.5M 104.0M 107.8M 111.7M 116.5M 117.5M 0 7.2M 13.1M 17.5M 22.3M 24.6M 33.3M 38.1M 41.7M 43.9M 49.1M 55.7M 60.4M 66.8M 72.0M 76.8M 82.3M 84.9M 90.1M 96.0M 98.6M 102.4M 104.6M 106.7M 109.0M Jul-24 Sep-24 Nov-24 Jan-25 Mar-25 May-25 Jul-25 Sep-25 Nov-25 Jan-26 Mar-26 May-26 Jul-26 CUM PLANNED PROGRESS CUM ACTUAL PROGRESS MONTHLY PLANNED MONTHLY ACTUAL
Slide 17
FINISHES 142
AL Alaya 'a Residential Cluster D
عقد الخرسانات و التشطيبات
PROGRESS REPORT
UP TO 1-9-2026

P4 PROJECT DETAILS

AL ALAYA 'A RESIDENTIAL - CLUSTER D
AL ALAYA Cluster D project photo
BEHIND SCHEDULE
CONTRACT VALUE
282,000,000 SAR
PLANNED PROGRESS
14.81%
ACTUAL PROGRESS
11.88%
SPI
0.80

Progress Performance

Planned
14.81%
Actual
11.88%
Variance
-2.93%

Schedule Status

18.33%ELAPSED
Elapsed18.33%
Remaining81.67%
Remaining Value248,498,400

MASTER PLOT OVERVIEW

PROJECT STATUS MAP
Master plot aerial view
PLOT : 093
PLANNED = 0%
ACTUAL = 0%
PLOT : 150
PLANNED = 14.81%
ACTUAL = 11.88%
PLOT : 149
PLANNED = 14.81%
ACTUAL = 11.88%
PLOT : 148
PLANNED = 14.81%
ACTUAL = 11.88%

SITE PROGRESS — DRONE FOOTAGE

Aerial site capture 1 of 3 — Cluster (D) Structure — Civil & Structural Works
SITE FOOTAGE 1/3
Clip 10:07
Source: on-site drone capture • Cluster (D) civil works

SITE PROGRESS — DRONE FOOTAGE

Aerial site capture 2 of 3 — Cluster (D) Structure — Civil & Structural Works
SITE FOOTAGE 2/3
Clip 20:10
Source: on-site drone capture • Cluster (D) civil works

SITE PROGRESS — DRONE FOOTAGE

Aerial site capture 3 of 3 — Cluster (D) Structure — Civil & Structural Works
SITE FOOTAGE 3/3
Clip 30:15
Source: on-site drone capture • Cluster (D) civil works

CLUSTER D S-CURVE

Dynamic curve generated from CLUSTER D S CURVE.xlsx
Source: S CURVE sheet
FINAL PLANNED
211.5M SAR
LATEST ACTUAL
22.2M SAR
LATEST ACTUAL MONTH
Aug-26
CURVE PERIOD
Apr-26 - Apr-28
0 57.1M 114.2M 171.3M 228.4M 1.2M 14.4M 4.8M 5.8M 5.9M 4.1M 6.3M 7.6M 9.1M 5.3M 4.2M 9.1M 10.5M 10.0M 13.2M 17.0M 17.3M 16.6M 17.6M 16.0M 11.8M 3.5M 0 0 0 9.4M 5.7M 2.9M 4.3M 1.2M 15.6M 20.4M 26.2M 32.1M 36.3M 42.6M 50.2M 59.3M 64.6M 68.8M 77.9M 88.4M 98.4M 111.6M 128.6M 145.9M 162.5M 180.1M 196.1M 208.0M 211.5M 211.5M 211.5M 211.5M 0 9.4M 15.1M 18.0M 22.2M Apr-26 Jun-26 Aug-26 Oct-26 Dec-26 Feb-27 Apr-27 Jun-27 Aug-27 Oct-27 Dec-27 Feb-28 Apr-28 Cum Planned Progress Cum Actual Progress Monthly Planned Monthly Actual
Cluster D progress image
CLUSTER D
Soliman Fakeeh Hospital
In Al Madina
PROGRESS REPORT
UP TO 01-SEP-2026

P1 PROJECT DETAILS

SOLIMAN FAKEEH HOSPITAL - AL MADINA
FAKEEH photo 1FAKEEH photo 2FAKEEH photo 3FAKEEH photo 4
COMPLETED
CONTRACT VALUE
115,000,000 SAR
PLANNED PROGRESS
100.00%
ACTUAL PROGRESS
100.00%
SPI
1.00

Progress Performance

Planned
100.00%
Actual
100.00%
Variance
0.00%

Schedule Status

100%ELAPSED
Elapsed100%
Remaining0%
Actual Value115,000,000
Remaining Value0

P1 PROJECT DETAILS

SOLIMAN FAKEEH HOSPITAL - AL MADINA
FAKEEH photo 5FAKEEH photo 6FAKEEH photo 7FAKEEH photo 8
COMPLETED
CONTRACT VALUE
115,000,000 SAR
PLANNED PROGRESS
100.00%
ACTUAL PROGRESS
100.00%
SPI
1.00

Progress Performance

Planned
100.00%
Actual
100.00%
Variance
0.00%

Schedule Status

100%ELAPSED
Elapsed100%
Remaining0%
Actual Value115,000,000
Remaining Value0

P1 PROJECT DETAILS

SOLIMAN FAKEEH HOSPITAL - AL MADINA
FAKEEH photo 9FAKEEH photo 10FAKEEH photo 11FAKEEH photo 12
COMPLETED
CONTRACT VALUE
115,000,000 SAR
PLANNED PROGRESS
100.00%
ACTUAL PROGRESS
100.00%
SPI
1.00

Progress Performance

Planned
100.00%
Actual
100.00%
Variance
0.00%

Schedule Status

100%ELAPSED
Elapsed100%
Remaining0%
Actual Value115,000,000
Remaining Value0

P1 PROJECT DETAILS

SOLIMAN FAKEEH HOSPITAL - AL MADINA
FAKEEH photo 13
COMPLETED
CONTRACT VALUE
115,000,000 SAR
PLANNED PROGRESS
100.00%
ACTUAL PROGRESS
100.00%
SPI
1.00

Progress Performance

Planned
100.00%
Actual
100.00%
Variance
0.00%

Schedule Status

100%ELAPSED
Elapsed100%
Remaining0%
Actual Value115,000,000
Remaining Value0
1 / 33